TYBCOM-SEM VI- COST ACCOUNTING l Contract Costing

 


Cost and Management Accounting

In this articles we are providing TYBCOM-SEM VI- COST ACCOUNTING l Contract Costing MCQ with Answer PDF. TYBCOM-SEM VI- COST ACCOUNTING l Contract Costing MCQ with Answer Semester VI. We are providing 200+ MCQ with answer.



Contract Costing

 

 

Meaning:

Contract Costing is that form of costing which applies where the work is undertaken to customer’s special requirements and order which is of a longer duration, and which is carried out at site which is different from contractor’s premises.

 

Under Contract Costing the work is usually of a constructional nature e.g. construction of Road, building, bridge and other civil engineering works etc.

 

A separate Account is opened for each contract and all the expenses incurred on it either at site of at office are charged to that particular Account.

 

Indirect expenses of Head Office are apportioned over all the contracts on hand on suitable basis.

 

Contract:

A contract is a legally enforceable agreement. Since the jobs involved are large, involving substantial money and time, a written agreement is entered into setting out the main terms and conditions of the contract.

 

Contractor:

The person who undertakes the job is the contractor.

 

Contractee:

The person for whom the job is being done is the contractee.

 

The Contract Price:

The contract price is the amount agreed to be paid by the contractee to the contractor as consideration for the job done. The contract price may be payable in lumpsum when work is completed. Alternatively, the amount may be paid in instalments as the work progresses. The amount of each instalment would depend on the amount of work done and certified by the architects.

 

Types of Contract:

Contracts are basically of two types:

a)      Fixed price Contract, where a fixed price is payable for completion of the entire job.

b)      Cost Plus Contract, where the contractee pays the contractor his actual costs plus a margin of profit or a fixed fee.

 

 

 

Work Certified:

It is that part of work completed for which the contractor gets the certificate of the Architect. In the case of large contracts, the contractor would expect the contractee to make payments of the contract price in instalments. He therefore, sends a part bill to the contractee as and when a portion of the work is completed. An Architect, appointed in terms of the contract, between the contract and contractee, scrutinizes the part bill; he certifies the work done for the purposes of payment. 

 

Work Certified appears on the credit side of the Contract Account.

Methods of Recording:

Method I

A)                In case of a small contract which is completed within one year

a)      When work is certified

Value of work certified is debited to Contractee’s A/c and credited to Contract A/c.

 

b)      When amount is received:

Amount received is debited to Cash A/c and credited to Contractee’s A/c.

 

Method II

B)                In case of large contract continuing for more than 1 year:

a)      When work is certified

Work certified is debited to work-in-progress A/c and credited to Contract A/c.

b)      When Cash is received:

The amount received is debited to Cash A/c and credited to Contractee’s A/c.

 

 

Work Uncertified:

Work uncertified is that cost of work done which relates to the period between the date of work certified and accounting year ending. At the end of the accounting period, not all the work done would have been certified by the architect. This would be so because the bill itself would not have been submitted by the contractor. Suppose the accounting period ends on 31st December. The contractor would have submitted his bills which would probably include all expenses incurred by him upto 10th December, and this might be certified for payment by the architect. The expenses incurred by the contractor between 11th December, and 31st December is the cost of Work Uncertified.

 

Work uncertified appears on the credit side of the Contract Account.

Journal entry:

Work-in-Progress A/c                                     Dr.

            To Contract A/c

 

Retention Money:

Retention money is that part of work certified which is retained by the contractee so as to safeguard his interest in case of future defects in the work done.

 

Profit on Incomplete contracts:

Where the contract is very large and is to continue over a number of years, it is usual to credit a part of the profit to the Profit and Loss Account each year i.e. even when the contract is not completed. 

The standard rules for taking such profits can be summarized as follows:

Sr.

No.

Extent of Work Completed

Profit to be Considered

1

Less than 25% 1% to 24%

No Profit is transferred to Profit & Loss A/c – entire profit is left as Reserve.

2

25% or more but less than 50%

25% to 49%

1/3rd of Notional Profit transferred to Profit & Loss A/c and balance is left as

Reserve

3

50% or more

50% & above

2/3rd of Notional Profit transferred to Profit & Loss Account and balance left as Reserve.

 

Sometimes profit is arrived by above method is further reduced by multiplying if further with:

            Cash Received

            Work Certified

Note: In case there is loss, full loss will be transferred to Profit & Loss Account.

 

Profit in case of Contract which are nearing successful completion:

A contract is said to be nearing successful completion when it has reached a stage that the contractor can estimate the further expenditure to be incurred to complete the contract. In this case, the future costs to be incurred on the contract can be estimated and therefore it would be possible to complete the Estimated Profit on the contract on a Prospective Basis. For this the total cost incurred on the contract to date are first calculated. To this is added an estimate of future cost determined on a conservative basis. The total of these two items will be deducted from the total Contract price. The difference will be the Estimated Profit on the Contract.

 

Escalation Clause:

This is a clause provided in the contracts to cover up an changes in the price of contract due to changes in price of raw materials and labour charges in utilization of factors of production. The object of this clause is to sage guard the interest of both sides against unfavorable change in the price.

 

 

 

Practical Problems

 

1.                  M/s. AB & Associates, a partnership firm comprising of partners A and B, undertook a contract to build a Bridge for Rs. 20,00,000 and commenced the work on 1-10-2008. The following is the Trial Balance of firm as on 30.09.2009:

 

Particulars

Debit Rs.

Particulars

Credit Rs.

Plant & Machinery

Office Buildings

Materials purchased

Sub-contracting charges

Interest

Office Overheads

 

 

2,50,000

3,00,000

4,20,000

1,40,000

80,000

10,000

50,000

 

12,50,000

Capitals: A

               B

Advanced from contractee

Bank overdraft

Outstanding wages

Creditors

Loans

1,20,000

80,000

6,00,000

1,40,000

10,000

1,50,000

1,50,000

 

12,50,000

 

Additional Information:

1.      Materials worth Rs. 4,00,000 were sent to site.

2.      Outstanding sub-contracting charges Rs. 20,000 at the year end.

3.      Allocate 50% of office overheads and 100& wages to contract.

4.      Plant and Machinery were used for the whole year on contract and provide depreciation @ 10% p.a.

5.      Partner A was entitled to salary of Rs. 20,000 for site supervision for the year.

Provide the same in Account.

6.      Contractee pays 75% of the work certified.

7.      Partner A and B share profit and losses in the ration 6:4 respectively.

8.      At the end of the year, work uncertified valued at Rs. 10,000 and material at site Rs. 20,000.

Prepare contract Account, Profit and Loss Account for the year ended 30.09.2009 and Balance sheet as on that date.

 

2.                  S. V. Construction Ltd. have obtained a contract for construction of a Building. The value of the contract is Rs. 45,00,000. The work commenced on 1st July, 2007 and was completed on 31st December, 2008. The following information relates to the contract:

 

Particulars

31.12.2008 Rs.

31.12.2007 Rs.

Materials issued

Direct wages

Direct Expenses

Indirect Expenses

Plant issued

Sub Contract charges

Work certified (cumulative)

Work uncertified

13,50,000

10,35,000

1,00,000

27,000

-

60,000

45,00,000

-

3,75,000

4,70,000

45,000

6,000

63,000

15,000

10,00,000

35,000

 

The above plant was specially issued for the contract. The residual value of the plant at the end of project was estimated to be Rs. 3,000.

The contractee has agreed to pay 90% of the work certified. The accounts are closed on 31st December, every year. Prepare:

a)      Contract Account

b)      Contractee Account

For two years 2007 and 2008. Show the relevant items in balance sheet as on 31.12.2007.

 

3.   Siddesh Construction Company has undertaken three contracts during the year and the following particulars are available as on 31st December, 2008:

 

Particulars

Contract A Rs.

Contract B Rs.

Contract C Rs.

Contract Price

Material issued to Contract

Labour

Sub-Contract Charges

Supervision Charges

Architect Fees

Insurance Charges

Work Certified

Work Uncertified

Amount received from Contractee

Closing Stock of Material

10,00,000

1,65,200

1,02,800

72,800

12,00

10,000

3,000

4,00,000

35,000

3,20,000

9,000

23,00,00

2,24,500

1,26,500

65,900

18,000

15,000

6,100

5,00,000

40,000

4,50,000

10,000

7,50,000

1,89,600

1,75,500

28,500

15,000

25,000

7,400

5,00,000

25,000

3,75,000

20,000

 

All contracts were commenced during the current year. Total depreciation on plants amounted to be Rs. 11,200 and allocate the same to all contracts in the ratio of work certified.

Prepare Contract Account. Show the calculation of profit transferred to Profit & Loss Account.

 

4.                  M/s. ABC Enterprises secured a contract for Rs. 45,00,000 and as per the Contract Agreement, the contractee would pay 90% of the work certified immediately upon Architects Certificate and the balance would be paid on completion of the contract. The work has commenced on 01.04.2008. The Actual Expenditure upto 31st March, 2009 and Estimated Expenditure upto 30th September, 2009 are as follows:

 

Particulars

Actual Expenditure upto 31.03.09 Rs.

Estimated

Expenditure upto 30.09.09 Rs.

Direct Materials

Indirect Materials

Direct Wages

Sub-contract charges

10,50,000

1,77,500

2,60,820

31,030

9,25,000

2,37,500

2,49,180

16,470

Architect Fees

Administrative Overheads

Hiring charges for equipment

Closing material at site

Certified work (Cumulative)

Uncertified work

57,500

2,14,390

1,45,610

1,29,000

22,50,000

56,250

90,000

1,37,110

79,390

-

45,000

-

 

A special machinery costing Rs. 4,00,000 was purchased for use on the contract. Its estimated scrap value at the end of the contract would be Rs. 40,000.

It was decided that the profit to be taken credit for the year ended 31.03.2009 should be proportion of the estimated net profit to be realized on the completion of the contract which the cash received for the year bears to the contract price. Prepare Contract Account for the year ended 31.03.2009 and estimated Contract Account.

 

5. Bhushan Contractors Ltd. obtained the contract to construct a building for Rs. 35,00,000. The contractee agrees to pay 90% of the work certified immediately upon the receipt of the certificate from the Architect and the balance amount would be paid in the completion of contract.

The work was commenced on 1st July, 2007 and completed on 30.09.2009.

A machine costing Rs., 45,000 was specially brought for use on contract and it would not fetch any value upon completion of the contract.

Further details are as follows:

 

Particulars

Years 2007

Years 2008

Years 2009

Work Certified (Cumulative)   (Rs.)

Work Uncertified                     (Rs.)

Materials Purchased

  Steel                                     (Tons)   Price per Ton                          (Rs.)

  Bricks                                   (Nos.) 

  Price per Brick                        (Rs.)

Wages                                       (Rs.)

Direct Overheads                      (Rs.)

Indirect Materials                     (Rs.)

Materials Returns

  Steel                                       (Ton)

  Bricks                                   (Nos.)

Materials Lost in Accident

  Steel                                     (Tons)

Materials Sold

  Steel                                     (Tons)

  Sale price per Ton                  (Rs.)

Scrapped Value of Bricks         (Rs.)

8,75,000

-

 

16

25,000

          16,000

5.00

4,25,000

17,500

7,500

 

1

1,000

 

- 

-

-

-

28,25,000

50,000

 

20

26,000

20,000

5.50

5,65,000

44,500

10,000

 

-

-

 

2

 

-

-

-

35,00,000

-

 

15

26,500

10,000

6.00

4,17,000

10,000

4,000

 

-

- 

-

 

4

27,000

18,000

 

You are required to prepare Contract Account and Contractee Accounts for the years 2007, 2008 and 2009 in the books of the company. The accounts are closed on 31st December, each year.

 

6. M/s. Rajendra constructions obtained a contract to build a Fly-over bridge at a contract price Rs. 150 Lacs.

The contractee agrees to pay 90% of value of the work done as certified by the architect immediately on receipt of the certificate and to pay the balance on completion of the contract. The contractor commenced the work on 1st May, 2008 and it is estimated to completed by 31st December, 2009. The actual expenditure upto 31st March, 2008 and subsequent estimated expenditure upto 31st December, 2009 is furnished below:

 

Particulars

Actual Expenditure upto 31.03.2009 Rs.

Estimated Expenditure 1.4.2009 to 31.12.2009 Rs.

Direct Materials

Indirect Materials

Direct Wages

Sub Contract Charges

Architect’s Fees

Administrative Overheads

Special Equipment Charges

Supervision Charges

Establishment Charges

Other Details

Cash Received

Closing Material at site

Uncertified Work

Certified work (cumulative)

33,50,000

5,60,000

8,42,000 98,000

1,84,000

6,50,000

4,86,000 10,000 p.m. 8,000 p.m.

Actual (Rs.)

67,50,000

4,10,000

1,80,000

75,00,000

28,00,000

7,00,000

7,95,000 52,000

2,84,000

4,50,000

2,54,000 12,000 p.m.

9,000 p.m.

Estimated (Rs.)

82,50,000

-

-

1,50,00,000

 

A special machinery costing Rs. 13,40,000 was bought for the contract and the estimated scrap value of the machinery at the end of the contract would be Rs. 1,40,000. It is decided that the profit to be taken credit for should be that proportion of the estimated net profit to be realized on completion of the contract which the certified values of work as on 31st March, 2009 bears to the total contract price. Maintain 2% provision for contingencies on total cost of contract (excluding such provision for contingencies). You are required to prepare the Contract Account for the period ending 31st March, 2009 and show your calculation of the profit to be credited to the Profit and the Loss Account for the period ended 31st March, 2009.

 

7.  The following information relates to a building contract undertaken by M/s. Asmit Ltd. for Rs. 10,00,000 and for which 80% of the value of work certified by the architect is being paid by the contractee.

 

Particulars

I Year

II Year

III Year

Material issued

Direct wages

Direct Expenses

Indirect Expenses

1,20,000

1,10,000

5,000

2,000

1,45,000

1,55,000

17,000

2,6,00

84,000

1,10,000

6,000

500

Work Certified

Uncertified Work

Plant Issued

Material on site

2,35,000

3,000

14,000

2,000

7,50,000

8,000

-

5,000

10,00,000

-

-

8,000

 

The value of plant at the end of I, II and III year was Rs. 11,200, Rs. 7,000 and Rs. 3,000 respectively. Prepare contract account for these three years.

 

8.  The following Trail Balance was extracted from the books of Apollo Contractor as on 31st December, 2008:

 

Particulars

Dr. Rs.

Cr

Rs.

Contractee’s Account

Buildings

Creditors

Bank

Capital Account

Materials

Wages

Expenses

Plant

Work in Progress 9Contract No. 837) (1.1.2008)

Contract No. 837 A/c (1.1.2008) (Unadjusted Profit)

 

 

-

1,00,000

-

35,000

-

1,00,000

70,000

37,000

2,50,000

1,00,000

-

 

6,92,000

3,00,000

-

62,000

-

3,00,000

-

-

-

-

-

30,000

 

6,92,000

 

Contract No. 837, which was in progress on 1st January, 2008, was completed on 31st March, 2008. Contract No. 838 commenced on 1st January, 2008.

Rs. 20,000 materials and Rs, 10,000 Wages were paid for Contract No. 837 site. Material Rs. 6,000 issued to Contract No. 838, but Rs. 3,000 worth was lost by accident, Rs. 60,000 Wages paid for Contract No. 838. Rs. 50,000 Plant was used in Contract No. 838 all through but plant costing Rs. 2,00,000 was used on Contract No. 838 from 1st April, 2008, prior to that, the above machinery was used in Contract No. 837. Rs. 4,000 materials were at site on Contract No. 838 at the end of the year. Provide 10% depreciation on the Plant and 2% on buildings.

Contract No. 837 was for Rs. 1,50,000 and certified work upto last year Rs. 1,00,000. The work has been certified upto the full extent, but payment has been received upto 80% of the certified amount. The balance has not been aid yet, nor has any entry been passed, on completion of the Contract.

 

 

Expenses are charged to Contracts on the basis of 50% of direct wages. The new contract is for Rs. 4,00,000 and 90% is paid on certification. The uncertified work of the contract s on 31st December, 2008 is estimated at Rs. 15,000.

You are required to prepare:

a)      Contract No. 837 Account

b)      Contract No. 838 Account

c)      Profit & Loss Account for 2008

d)      Contract Ni. 837 Contractee’s Account

e)      Contract No. 838 Contractee’s Account

f)       Balance Sheet as on 31st December, 2008.

 

9. A undertook a contract for Rs. 5,00,000. He incurred the following expenses during the year:

 

Particulars

Rs.

Materials issued from Stores

Materials purchased for the Contract

Plant installed at Cost

Wages paid

Wages accrued due on 31.12.2008

Direct Expenses paid

Direct Expenses accrued due on 31.12.2008

Establishment Expenses

50,000

45,000

35,000

1,00,000

40,000

10,000

2,500

6,500

 

Of the plant and material charged to the contract, the plant which cost Rs. 2,000 and the materials costing Rs. 1,500 were lost. Some of the material costing Rs. 2,000 was sold for Rs. 2,500. On 31st December, 2008, the plant which cost Rs. 500 was returned to the stores and a part of the plant which cost Rs. 200 was so damaged as to render itself useless.

The work certified was Rs. 2, 40,000 and 80% of the same was received in cash. The cost of work done but uncertified was Rs. 1,000. Charge 10% p.a. depreciation on plant and prepare contract account for the year ended 31st December, 2008 by transferring to Profit and Loss Account the portion of profit, if any, which you think reasonable.

Show also the particulars relating to the contract in the balance sheet of the contractor as on 31st December, 2008.

 

Following information relates to a building contract commenced on 1st April 2014 for Rs. 10,00,000.

Particulars

2014-15 Rs.

2015-16 Rs.

Materials Issued

Direct Wages

Outstanding Wages

Sub-Contract Charges

Indirect Expenses

General Expenses

Supervision Charges

Work Certified (Cumulative)

Work Uncertified

Materials at site at the end

3,02,000

2,00,000

20,000

12,000

10,000

6,000

10,000

7,50,000

8,000

5,000

84,000

1,00,000

 

10,000

 

1,400

5,000

10,00,000

 

 

Plant Issued

Materials returned to stores

Cash received from the Contractee during the year

14,000

2,000

6,00,000

2,000

5,000

4,00,000

The value of Plant at the end of 2014-15 and 2015-16 was Rs. 7,000 and Rs. 5,000 respectively.

Prepare Contract Accounts for the years 2014-15 and 2015-16.

 

11. Saurav Ltd. obtained two contracts viz., A and B. Contract A commenced on 1st October, 2014 and Contract B started on 1st December 2014. Following information was extracted from their books for the year ended 31st March 2015.

 

Particulars

Contract A Rs.

Contract B Rs.

Contract Price

Cash Received

Plant issued at commencement

Work Certified

Work Uncertified

Direct Wages

Supervision Charges

Administrative Overheads

Sub-Contract Charges

Electricity Charges

Architect’s Fees

Indirect Materials

Direct Materials

Direct Materials returned to Stores

Direct Materials at the site at the end of the period.

 

70,00,000

11,20,000

22,50,000

14,00,000

52,000

2,95,000

1,36,500

2,72,500

63,700

48,800

52,000

1,47,000

3,58,000

14,000

73,000

15,00,000

7,65,000

12,00,000

9,00,000

28,000

1,77,500

30,700

1,47,500

 

 

27,000

1,62,600

1,99,200

 

54,000

Provide depreciation @20% p.a. on the original cost of Plant.

Prepare Contract A and Contact B Account for the period ended 31st March ended 2015.


Multiple Choice Questions

1. Contract costing is the basic method of 
a) Historical costing
b) Specific order costing
c) Process costing
d) Standard costing

2. Contract costing is a variant of _________ Costing.
a) Job
b) Process
c) Unit
d) Batch

3. Contract costing usually applicable in 
a) Constructional work
b) Textile Mills
c) Cement Industries 
d) Chemical Industries

4. __________ is the person for whom the Contract job is undertaken.
a) Contractor
b) Contractee
c) Sub-contractor
d) Job-worker

5. __________ is not a contract cost.
a) Direct wages
b) Depreciation of plant
c) Sub-contractors' fees
d) Architects' certificates

6. The degree of completion of work is determined by comparing the work certified with 
a) Contract price
b) Work in process
c) Cash received on contract
d) Retention money

7. In contract costing credit is taken only for a part of the profit on 
a) Completed contract
b) Incomplete contract
c) Work uncertified
d) Work Certified

8. In contract costing payment of cash to the contractor is made on the basis of 
a) Uncertified work
b) Certifies work
c) Work in process 
d) Retention money

9. The cost of any sub contracted work is 
a) A direct expenses of a contract and is debited to the contract account
b) A indirect expenses of a contract and is debited to the contract account
c) A direct expenses of a contract and is debited to the client account
d) A indirect expenses of a contract and is debited to the client account

10. Progress payments received by the contractor from the client are
a) Debited to the contract account
b) Credited to the contract account
c) Debited to the client account
d) Credited to the client account

11. Retention money is equal is to 
a) Work certifies less work uncertified
b) Contract price less work uncertified
c) Work Certified less payment received by contractor
d) None of the above

12. Material supplied by the Contractee
a) is debited to the Contract Account
b) is ignored in the Contract Account
c) is credited to the Contract Account
d)  is debited to the Contractee's Account

13. Cost of material lost or destroyed
a) is credited to the Contract Account
b) is debited to the Contract Account
c) is debited to the costing profit and loss account
d) is credited to the costing profit and loss account

14. Work certified valued at 
a) Cost price
b) Market price
c) Cost or market price whichever is less
d) Estimated price

15. Value of Work Certified Less Profit =
a) Work in progress
b) cost of work certified
c) Retention money
d) Cost of uncertified work

16. The Total value of work completed during an accounting year is equal to 
a) Work certified + Progress payment Received
b) Work certified + Work uncertified
c) Work certified + Retention money
d) None of the above

17. Notional profit is equal to 
a) Work certified Less Cost of work certifies
b) Work certified Less Cost of work completed
c) Payment received Less Work certified
d) None of the above

18. Work-in-progress at year end is equal to 
a) Only closing stock of materials
b) only work certified
c) only Work uncertified
d) The total of all the above

19. Work certified less than 25% of the contract price. The transfer to P&L A/c will be 
a) 1/3 rd' of Notional profit
b) NIL
c) 2/3 rd' of the Notional profit
d) 100% of Notional profits

20. Work certified is between 25% and 50% of the contract price. The transfer to P&L A/c will be 
a) 1/3 rd' of Notional profit, reduce in the ratio of cash received to work certified
b) NIL
c) 2/3 rd' of the Notional profit, reduce in the ratio of cash received to work certified
d) 100% of Notional profits

Cost and Management Accounting

Contract Costing


Multiple Choice Questions

1. Contract costing is the basic method of 
a) Historical costing
b) Specific order costing
c) Process costing
d) Standard costing

2. Contract costing is a variant of _________ Costing.
a) Job
b) Process
c) Unit
d) Batch

3. Contract costing usually applicable in 
a) Constructional work
b) Textile Mills
c) Cement Industries 
d) Chemical Industries

4. __________ is the person for whom the Contract job is undertaken.
a) Contractor
b) Contractee
c) Sub-contractor
d) Job-worker

5. __________ is not a contract cost.
a) Direct wages
b) Depreciation of plant
c) Sub-contractors' fees
d) Architects' certificates

6. The degree of completion of work is determined by comparing the work certified with 
a) Contract price
b) Work in process
c) Cash received on contract
d) Retention money

7. In contract costing credit is taken only for a part of the profit on 
a) Completed contract
b) Incomplete contract
c) Work uncertified
d) Work Certified

8. In contract costing payment of cash to the contractor is made on the basis of 
a) Uncertified work
b) Certifies work
c) Work in process 
d) Retention money

9. The cost of any sub contracted work is 
a) A direct expenses of a contract and is debited to the contract account
b) A indirect expenses of a contract and is debited to the contract account
c) A direct expenses of a contract and is debited to the client account
d) A indirect expenses of a contract and is debited to the client account

10. Progress payments received by the contractor from the client are
a) Debited to the contract account
b) Credited to the contract account
c) Debited to the client account
d) Credited to the client account

11. Retention money is equal is to 
a) Work certifies less work uncertified
b) Contract price less work uncertified
c) Work Certified less payment received by contractor
d) None of the above

12. Material supplied by the Contractee
a) is debited to the Contract Account
b) is ignored in the Contract Account
c) is credited to the Contract Account
d)  is debited to the Contractee's Account

13. Cost of material lost or destroyed
a) is credited to the Contract Account
b) is debited to the Contract Account
c) is debited to the costing profit and loss account
d) is credited to the costing profit and loss account

14. Work certified valued at 
a) Cost price
b) Market price
c) Cost or market price whichever is less
d) Estimated price

15. Value of Work Certified Less Profit =
a) Work in progress
b) cost of work certified
c) Retention money
d) Cost of uncertified work

16. The Total value of work completed during an accounting year is equal to 
a) Work certified + Progress payment Received
b) Work certified + Work uncertified
c) Work certified + Retention money
d) None of the above

17. Notional profit is equal to 
a) Work certified Less Cost of work certifies
b) Work certified Less Cost of work completed
c) Payment received Less Work certified
d) None of the above

18. Work-in-progress at year end is equal to 
a) Only closing stock of materials
b) only work certified
c) only Work uncertified
d) The total of all the above

19. Work certified less than 25% of the contract price. The transfer to P&L A/c will be 
a) 1/3 rd' of Notional profit
b) NIL
c) 2/3 rd' of the Notional profit
d) 100% of Notional profits

20. Work certified is between 25% and 50% of the contract price. The transfer to P&L A/c will be 
a) 1/3 rd' of Notional profit, reduce in the ratio of cash received to work certified
b) NIL
c) 2/3 rd' of the Notional profit, reduce in the ratio of cash received to work certified
d) 100% of Notional profits

21. Work certified is between 25% and 50% of the contract price. The transfer to P&L A/c will be 
a) 1/3 rd' of Notional profit, reduce in the ratio of cash received to work certified
b) NIL
c) 2/3 rd' of the Notional profit, reduce in the ratio of cash received to work certified
d) 100% of Notional profits 

22. The entire contract is complete. The transfer to P&L A/c will be 
a) 1/3 rd' of Notional profit
b) NIL
c) 2/3 rd' of the Notional profit
d) Entire profit

23. If a contact is 40% complete, credit taken to the profit and loss account is 
a) 40% of the notional profit
b) a) 1/3 rd' of Notional profit, reduce in the ratio of cash received to work certified
c) NIL
d) 2/3 rd' of the Notional profit, reduce in the ratio of cash received to work certified

24. Value of work certified Rs. 5,00,000 
Cost of work to date Rs. 4,00,000
Cost of work not yet certified Rs. 1,00,000        
Notional Profit is 
a) Rs. 1,00,000
b) NIL
c) Loss Rs. 1,00,000
d) Rs. 2,00,000

25. The total profit on a contract for Rs. 3,00,000 is Rs. 60,000 and the contract is 60% complete and has been certified accordingly. The retention money is 20% of the certified value, then the amount of profit that can be prudently certified to Profit and Loss Account
a) Rs. 60,000
b) Rs. 36,000
c) Rs. 28,800
d) Rs. 48,000

26. Contract cost Rs. 2,80,000,    Contract value Rs. 5,00,0000,    Cash received Rs. 2,70,000,    Uncertified work Rs. 30,000
Deduction from bills by way of retention money 10%.
How much profit, if any, you would take to the profit and Loss account?
a) Rs. 50,000
b) Rs. 33,333
c) Rs. 30,000
d) NIL


___________________________________________________________________________________

Post a Comment

0 Comments